The Construction of the State Power Investment Xuwen Capacity Increasing Project successfully Completed

16

-

10

-

2024

Recently, the impeller docking of the Xuwen Capacity Enhancement Offshore Wind Farm Project was completed and passed the acceptance of the four parties, marking the successful completion of the construction of the project undertaken by the Guangzhou Salvage Bureau. CFM participated  such project. 

 

A total of 25 wind turbines with a single capacity capacity of 12 MW will be built in the 300MW capacity expansion project of Zhanjiang Xuwen Offshore Wind Farm, and 1 set 220 kV offshore booster station will be built. Our bureau is responsible for all the work involved in the transportation and installation of wind turbine foundation and tower, the transportation and construction of jacket foundation of booster station, jacket installation, grouting, installation of booster station blocks, monitoring and acceptance, etc. Since the beginning of the winning of the project, the project team has overcome difficulties such as late start-up time and tight construction period, and has worked together sincerely and worked hard to promote the quality and efficiency of project construction.      

 

The successful completion of the hoisting construction of the whole site of the wind turbine marks a solid step towards the goal of full capacity grid connection of the project. After the project is put into operation, it is expected to generate 899 million kilowatt hours of electricity per year, equivalent to the annual basic electricity consumption of 370,000 households, save about 272,000 tons of standard coal and reduce carbon dioxide emissions by 723,300 tons per year, with significant social and environmental benefits.

 

Review of the construction nodes of the project >>>

Completion of the first pile

2023.09.20

 

Completed the construction of the jacket foundation of the booster station

2024.04.14

 

Completed the first wind turbine hoisting industry

2024.05.13

 

Completed the hoisting construction of the upper block of the booster station

2024.05.29

 

The construction of the monopile foundation was completed

2024.06.30